WILLISTON, N.D. – Monday, April 21, Reede Construction, Inc. began Phase 1 of a major roadway improvement project on U.S. Highway 2 and 2nd Avenue West, affecting traffic in the heart of Williston.
As part of this first phase, all inside lanes in both directions will be closed, reducing traffic to a single lane each way. This lane closure will remain in effect until further notice as crews begin necessary preparation and reconstruction work.
This project, commissioned by the North Dakota Department of Transportation and the City of Williston, is part of a broader initiative to improve access to the growing Williston Square development and support long-term infrastructure goals.
Project Scope
Reede Construction will be reconstructing U.S. Highway 2 from 9th Avenue West to north of 35th Street, with the following enhancements:
- Expanded roadway capacity to support increased traffic volume
- Upgraded intersections for improved traffic flow and safety
- New pedestrian features, including sidewalks and crosswalks
- Improved lighting and drainage systems to meet modern infrastructure standards
Construction Timeline
- Initial Demolition Began: March 17, 2025 (structures in the acquired right-of-way)
- Phase 1 Field Work Begins: April 21, 2025
- Substantial Completion Expected: October 25, 2025
- Final Completion (Permanent Striping): June 30, 2026