The Material Source Approval process relates to the cultural and environmental review of aggregate, borrow, and riprap source locations including support activities. Note, this does not include testing of materials. If you are looking for material testing information, go to Materials and Research.
About the Material Source Approval Process
The process changed as of 2009 - the old process was based on projects, while the new process is based on locations. The purpose of the new process is to streamline the review process, in response to feedback from stakeholders involved in the process.
- Check the NDDOT Material Source Certificate of Approval page to see if the location you intend to use has been issued a Certificate of Approval (COA). If a COA has been issued, the Applicant shall print and submit the COA to the Project Engineer, who will make it part of the project record. Material Source Locations that are included in the plans or bidder's proposal do not need to be reprinted at the time of construction. All conditions listed on a COA must be followed.
- If the location has not been approved, send us an email with a completed SFN 58466: NDDOT Material Source Approval Request Form and map. If there are any issues with a location requiring further coordination with State or Federal Agencies, the NDDOT Environmental and Transportation Services Division staff will contact the applicant. After the source has been approved, a COA will be published on the NDDOT Material Source Certificate of Approval Website. The Applicant shall print and submit the COA to the Project Engineer. The Project Engineer will make it part of the Project Record.
You may contact staff about this process by phone at 701-328-2731 or by using the following link: Material Source Section
Site Approval and Approved Sites
- Material Source Certificates of Approval
- Threatened and Endangered Species
If your site doesn't have a valid Certificate of Approval (COA) and/or hasn't been issued a COA within the past three years you must submit a new request. Complete the following steps to submit a new request.
Frequently Asked Questions
United States Geologic Survey Topographic Maps (quad maps) and/or aerial images are preferred. The maps should clearly identify the location to be used and published at a scale greater than 1:10,000 but less than 1:24,000. Please include the Township, Range, and Section on the map and verify that it reflects the legal description provided on the Material Source Approval Request Form. Maps are preferred in color; however black and white maps will be accepted, provided the site is clearly identifiable. Please do not fax requests. Most maps that are sent via fax are not legible and will result in a delay. The clarity and definition of the map reduces potential delays, including but not limited to U.S. Fish and Wildlife Service (USFWS) Easement coordination and additional cultural reviews.
The department is required to comply with all federal and state laws and regulations which govern the protection of wetlands protected under the Clean Water Act and Executive Order 11990, threatened and endangered species protected under the Endangered Species Act, and Section 4(f) properties protected under Section 4(f) of the Department of Transportation Act.
In addition, the department must comply with Section 106 of the National Historic Preservation Act (NHPA). Federal law, such as the Endangered Species Act, requires that the potential of any activity performed in conjunction with a transportation project be evaluated before initiating such activity. Material sources are considered part of the Federal undertaking for transportation projects in North Dakota. Material sources include riprap and material from commercial sources, and any other area of planned ground disturbing activities, such as staging area(s), plant site(s), stockpile area(s), waste site(s) and haul road(s). The Department is also required by a condition in the Section 404 permits issued by the United States Army Corps or Engineers (USACE), “to provide the locations of all material sources to be utilized for each phase of construction, along with documentation of cultural and endangered species clearance for each site, prior to use.”
The contractor must present the project engineer with a valid (current year) COA for each contractor optioned area to be used on a NDDOT project. If a COA posted on the web does not reflect the current year, contact the Environmental and Transportations Services Division. COAs are available on the NDDOT Material Source Certificate of Approval Website. If a COA is not available for the source, the contractor must submit SFN 58466: NDDOT Material Source Approval Request Form. Be sure to attach a map showing the boundary of the area you intended to be used. Every location that is used on a project must have a COA.
Within 5 working days of receipt of the information from the applicant, the Environmental Services Section will meet with the U.S. Fish and Wildlife Service to obtain clearance. If further review is required, the Environmental Services Section will coordinate with the local U.S. Fish and Wildlife Service Wetland Management District office to review the location(s) in the field. The purpose of this is to identify avoidance areas and areas that can be used. This additional review in the field may take up to an additional 10 working days to schedule. Seasonal limitations may apply.
The project engineer is responsible for ensuring that all contractor optioned areas have been issued a COA prior to utilizing the site and enforce all site conditions listed on the COA. In addition, Project Engineer will make the COA part of the project record for each material source used on a project. Material Source Locations that are included in the plans or bidders proposal do not need to be reprinted at the time of construction, but conditions listed on the COA must be followed.
The project engineer shall contact the NDDOT and ask for the Environmental Services Section 701-328-2600.
Construction noise and activity can disturb the species, therefore until the U.S. Fish and Wildlife Service observes the species and physical surroundings, no work can continue.
The department must coordinate with federal and state agencies on the proposed clearance. In some cases we need to work with out-of-state records. It may take less than or more than 30 days to complete, but on average it can take 30 days to complete the Material Source Approval process. Seasonal limitation may apply.
Federal and state laws require reporting certain types of discoveries within 24 hours. Depending on what you discover, and the location, the department may be required to consult with law enforcement, tribes, the State Historic Preservation Officer, and the Advisory Council. The quicker the discovery is reported, consultation can begin and the quicker work may resume on the project. The same holds true with threatened and endangered species; the Project Engineer must notify the Environmental Section immediately. The department needs to notify the U.S. Fish and Wildlife Service within 24 hours of a sighting. The quicker the sighting is reported, consultation can begin and the quicker work may resume on the project.
Standard Specifications
Mapping Links
- Quick Maps (html)
- Quick Maps allows the user to create downloadable maps in different file formats for use in reports and design documents. The restricted county haul roads are included as a GIS layer.