03/31/2020 02:00 PM

NDDOT seeks comments on 2020 Statewide Transportation Improvement Program (STIP) Amendment

The North Dakota Department of Transportation (NDDOT) is seeking comments on amendments to the 2020-2023 State Transportation Improvement Program (STIP) for addition of federal funding to a previously published program in 2020 and a previously unpublished project.

  1. The total estimated cost for the 2020 individual preliminary engineering for various statewide locations has increased from $2,000,000 to $12,000,000.
  2. Preliminary engineering for four-laning of US 85 from Theodore Roosevelt National Park entrance to County Road 30 (23rd St NW), RP 127.21 to RP 139.44. Total Cost for preliminary engineering: $3,800,000.

The public is invited to view the current STIP on the NDDOT’s website at www.dot.nd.gov by clicking on “Publications” on the top of the page, then clicking on the “2020-2023 Final STIP (Statewide Transportation Improvement Program)” link under the Plans and Reports section.

Comments should be sent no later than April 15, 2020 to Logan Beise at NDDOT, 608 E Boulevard Ave, Bismarck, ND 58505-0700, or sent via email lsbeise@nd.gov with “2020 State Federal-Aid Roadway Projects” in the subject line.

For more information: Logan Beise, (701)328-2139 or NDDOT Communications, (701)328-4444